建设工程英语选修课作业。
1、please give some examples from the sentences about unit six:engineering project(no less than10).[
1 、a project execution is usually divided into some elementary phases, such as: engineering, procurement and transportation, and field construction.
一个工程项目的实施通常可分为几个基本阶段:工程设计、采购和运输、以及现场施工。
2 、the contract number of this project is cjc78-8.这个项目的合同号是cjc78-8。
3 、the seller (vendor) is toyo engineering corporation (tec) of japan.
卖方(卖主)是日本的东洋工程公司。(简称tec)
4 、the buyer (customer, client)is china national technical import corporation.(cntic)
买方(主顾、顾客)是中国技术进口总公司。(简称cntic)
5 、china national chemical construction corporation (cnccc) contracts for domestic and overseas chemical projects.中国化工建设总公司(简cnccc)承包国内和海外的化工工程。
6 、are you the seller’s representative on the job site?你是卖方的现场代表吗?
7 、i am the buyer’sgeneral representative.(gr)我是买方的总代表。(简称gr)
8 、it is an inquiry (commercial and technical proposal, approval, agreement ,protocol, annex, technical appendix) about this project.
这是这个项目的询价书。(商务和技术**书、批准书、协议、会议记录、附加条件、技术附件)
9 、there is much information in the technical proposal, which including: process flow, process description, capacity of the plant, performance of the product.
技术**书中有很多资料,包括:工艺流程、工艺说明、生产能力、产品特性等。
10 、the project team normally consists of project engineer, design engineer, schedule engineer, and various specialists.
项目工作组通常包括有项目工程师、设计工程师、计划工程师、以及各类专家。
11 、we can evaluate the results of field construction by four criteria, which are quality, time, cost and safety.
我们可以通过四个指标来评价现场施工的成绩,即质量、时间进度、费用和安全。
12 、i am responsible for the technical (scheduling, inspection, quality control) work of this project.( area)我负责这个项目(区域)的技术(技术、检查、质量控制)工作。
13 、would you tell us the technical characteristic about this project?
你能告诉我们有关这个工程项目的技术特性吗?
14 、please give a description about this project.请对这个工程项目作一个叙述说明。
do you h**e any reference materials about this project?你有关于这个工程项目有参考资料。
2、please give some examples from the sentences about unit seven:planning and scheduling(no less than10).[
1 、we should work according to the overall schedule chart (the construction time schedule) of the project. 我们应该按照工程项目的总进度表(建设进度表)工作。
2 、the effective date of this contract will begin from dec. 30th, 2007.
这个合同的有效期将从2023年12月30日开始。
3 、the seller will provide preliminary (final) technical documents for buyer in may.
卖方将于五月份向买方提供初步(最终)技术文件。
4 、the basic (detailed) process design will be issued before august.
基本的(详细的)工艺设计资料将于八月前发出。
5 、r major planning items contain estimating of cost and construction schedule.
我们主要的计划工作项目包括费用预算和施工进度。
6 、we shall h**e a design collecting (preliminary design, final design) meeting next month.
下个月我们将召开设计数据收集(初步设计、最终设计)会议。
7 、field erection work (civil work) will begin in october this year and complete on june first next year.现场安装工作(土建工作)将自今年十月开始至明年六月一日完工。
8 、the date of acceptance of this plant will be april sixth, 2008.
这座工厂的交工验收期将在2023年4月6日。
9 、the seller’s operating group (a crew of specialists) will remain on the job until guarantees are met.卖方操作组(专业工作组)将在现场,一直工作到生产符合保证条件。
10 、we must take the plant through the test run and finally into commercial operation.
我们必须使工厂通过试运转并最终投入工业生产。
11 、every month we shall establish construction schedule每个月我们都要制订建设进度计划。
12 、we shall also make the project schedule report every day.我们也将每天提出项目进度报告。
13 、we are going to begin this work tomorrow. (next week, next month).我们准备明天(下周、下月)开始这项工作。
14 、we must take this work plan into consideration.我们必须考虑这个工作计划。
3、please give some examples from the sentences about unit eight:technical documents and drawings(no less than10).[
1 、how many drawings are there in the set?这套图纸有几张?
2 、is this a copy for reproduction?这是一份底图吗?
3 、what is the edition of this drawing?这张图纸是第几版?
4 、is this drawing in effect?这张图纸有效吗?
5 、is this a revised edition?这是修订版吗?
6 、will it to be revised yet?这张图还要修订吗?
7 、are there some modifications (revisions) on the drawing?这张图上有些修改(修正)吗?
8 、the information to be placed in each title block of a drawing include: drawing number, drawing size, scale, weight, sheet number and number of sheets, drawing title and signatures of persons preparing, checking and approving the drawing.
每张图纸的图标栏内容包括:图号、图纸尺寸、比例、重量、张号和张数、图标、以及图纸的制图、校对、批准人的签字。
建设工程英语
建设工程英语选修课作业。1 please give some examples from the sentences about unit six engineering project no less than10 1.a project execution is usually divided ...
工程建设现场英语五百句
内容目录。工程建设现场英语五百句 1 一 问候和介绍 36句 2 二 交谈语言 24句 3 三 日期和时间 20句 4 四 天气和环境 20句 5 五 在会议上 34句 6 六 工程项目 20句 8 七 计划与进度 20句 9 八 技术资料和图纸 34句 10 九 公用工程 20句 12 十 施工现...
工程建设现场英语五百句
工程建设现场英语五百句 1 2007 03 20 16 35工程建设现场英语五百句 1 目录。一 问候和介绍 36句 greetings and introductions 二 交谈语言 24句 talking about languages 三 日期和时间 20句 dates and times ...